Timescale
The principles of design and development for MK West were agreed by Milton Keynes Partnership with the Outline Planning Consents due to be released shortly.Gallagher want to keep you up to date with the timescale for the development.
Month | Activity | |||||||
September/October 2007 | Outline Consents Released | |||||||
November 2007 | Design Codes Submitted | |||||||
December 2007 | Main Road and Drainage Application | |||||||
June/July 2008 | Commence Primary Infrastructure on Areas 10 and 11 | |||||||
June/July 2008 | First Individual application from house builders for parcels of land | |||||||
November/December 2008 | First house building commences | |||||||
June 2009 | First MK West residents move in | |||||||