Timescale

The principles of design and development for MK West were agreed by Milton Keynes Partnership with the Outline Planning Consents due to be released shortly.
Gallagher want to keep you up to date with the timescale for the development.


The provisional timetable below shows scheduled key activity timings:
Month Activity
September/October 2007 Outline Consents Released
November 2007 Design Codes Submitted
December 2007Main Road and Drainage Application
June/July 2008 Commence Primary Infrastructure on Areas 10 and 11
June/July 2008 First Individual application from house builders for parcels of land
November/December 2008 First house building commences
June 2009 First MK West residents move in